How to import exam timetable into Synergetic
Issue
There are lot of things to consider when importing the exam timetable into synergetic.
- Firstly, you will need to create a new Timetable group in luTimetableGroup look up table. Set the Cycle days, Actual Days in Week and the number of Periods in the day.
- Then you will need to create a new Exam File Type in luFileType look up table and make sure the "Timetable Flag" is selected in the look up table.
- Once the File type and Timetable group is created, go to Timetable maintenance and select the Exam File Type.
- You will need to create Timetable Definition for the Exam File type in the Timetable definition tab
- Link Year levels to the Exam Timetable Group in the Timetable Group tab
- Add Calendar events in the Calendar events tab by setting up the dates of the exam and the Calendar type it should follow.
- Then link the exam timetable group along with the timetable day.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article