To schedule a report to run several times on its designated day:
- Schedule the report to run on a daily, weekly or monthly basis.
- Select Occurs every:.
- Select the number of minutes between report runs. For example:
• 1: run the report every minute
• 60: run the report every hour. - Select the time of day you want the first report run to occur.
- Select the time of day you want the report runs to end.
- Click .
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article